PENTA’s smart and practical cement plant design was able to shave around 30% off the turnkey bids this client received from OEM’s without compromising quality.

This Engineering, Procurement, and Construction Management (EPCM) project included a 1500 mtpd wet process conversion to a 2100/2500 mtpd dry process line, preliminary and final drawings, construction management, commissioning and start-up assistance, and contract close out.

New equipment designed, procured, and installed:

  • Cross Bar Cooler
  • Vertical Raw Mill
  • Baghouse
  • Blending Silo
  • Conversion of Raw Mill to Pre-Grinding
  • All Materials Handling